SP phases 2 & 3 go beyond capacity in gas production
The nominal production capacity of each phase stands at 25 million cu. m per day, he said, adding, each phase presently produces over 26.5 million cu. m gas in a day. Each phase also produces 80,000 barrels condensates and 400 tons sulfur, he said.
The same increase of production (7 percent) has been also designed for the phases 4 and 5, he noted. The current production is the same as the nominal capacity as well, he added.
He further announced phases 6, 7, and 8 of the southern gas field are to become operational in the current Iranian year (started March 21, 2006).
According to the latest report issued by Pars Oil and Gas Company, the total condensate exports of phases 1-5 stand at 159,701,000 barrels. In addition, nearly 98 million cu. m natural gas produced at these phases has been so far injected into the national grid.
SP phases 9, 10 progress 46%
Sahel Tangestani, director of planning affairs at Oil Industries Engineering and Construction Company (OIEC) told the Mehr News Agency the development project of South Pars phases 9 and 10 have progressed by 46 percent.
Constituting of the onshore and offshore parts, the project should become operational by or in 2008; however, it is predicted to face a delay in commissioning due to the financial problems, Tangestani noted.
Being implemented by OIEC and a foreign company, the onshore part of the project has progressed by 42 percent, he explained, putting Iranian company’s share at 40 percent of the project’s whole value.
The total value of the project is around $1.6 billion and the engineering operations, construction, and installation are currently underway in these phases.