First platform of South Pars phases 22-24

Total:4

  • SP 2019-11-13 15:39

    3rd platform of SP phases 22-24 installed

    TEHRAN- Platform SPD-23, which is the third platform of the phases 22, 23, 24 of South Pars gas field (in the Persian Gulf) development project was installed at its designated offshore place in phase 23, on Tuesday.

  • SP 22-24 2019-10-11 15:02

    Last platform of South Pars phases 22-24 loaded

    TEHRAN- Platform SPD-24B, which is the last platform of the phases 22, 23, 24 of developing South Pars gas field (in the Persian Gulf), was loaded at Sadra yard in the southwestern province of Bushehr on Thursday.

  • SP 2019-08-16 18:25

    3rd platform of SP phases 22-24 loaded

    TEHRAN- Platform SPD-23, which is the third platform of the phases 22, 23, 24 of South Pars gas field (in the Persian Gulf) development project was loaded at Sadra yard in the southwestern province of Bushehr on Wednesday.

  • First platform of South Pars phases 22-24 2019-01-13 21:32

    First platform of South Pars phases 22-24 starts operation

    TEHRAN- The first platform of phases 22-24 of South Pars gas field starts operation, Farhad Izadjou, the operator of these phases, announced.